Batangas – Makban 230KV Transmission Line Project – BTRP SCH II

  • Client/ Contractor: TransCo/ AER
  • Date Awarded/ Completed: October 2007 – December 2007
  • Works done: Tower Erection – 6 Towers and Uplifting of Span BM- 24
Alt

69KV Steel Poles of Temporary By-Pass for Tower 99-102 of Naga-Daraga T/L

  • Client/ Contractor: TransCo/ FABMIK
  • Date Awarded / Completed: October 2007 – November 2007
  • Works done: Construction and Erection of Steel Poles (58 Poles – 6KM)
Alt

Sta. Magdalena – Naga HVDC 230KV Transmission Line Project

  • Client: NGCP
  • Date Awarded/ Completed:May 3, 2010–July 23, 2010
  • Works done: Riverbank Protection at Tower 50, Embankment Slope Protectionfor Tower 33 and Tower 106
Alt

Malitbog – Tabango 230KV DC/ST Transmission Line

  • Client: TransCo
  • Date Awarded/ Completed: July 2008–November 2008
  • Works done: Slope Protection for Tower 60
Alt

Construction of Perimeter Fence for 4 Repeater Station

  • Client: TransCo
  • Date Awarded/ Completed:August 2007 – December 2007