Daraga Substation Expansion 50MVA

  • Client/ Contractor: TransCo/ SLDCC
  • Date Awarded/ Completed:March 2006–September 2006
Alt

69KV Steel Poles of Temporary By-Pass for Tower 19-23 of Bacman-Daraga T/L

  • Client/ Contractor: TransCo/ FABMIK
  • Date Awarded/ Completed: October 2007 – November 2007
  • Works done: Construction and Erection of Steel Poles (34 Poles – 2.7KM)
Alt

Reconstruction of Damaged ACSR at Plant D Tie Line including Splicing and Clipping of Jumper

  • Client: Laguna International Industrial Park Association, Inc.
  • Date Awarded/ Completed: April 2007 – August 2007
Alt

Batangas – Makban 230KV Transmission Line Project – BTRP SCH II

  • Client/ Contractor: TransCo/ Star Infrastructure & Development Projects
  • Date Awarded/ Completed: October 2006 – December 2006
  • Works done: Uplifting of Span BM-24
Alt

San Lorenzo – Mahabang Parang S/S 230KV Transmission Line Reinforcement Project – SCH I

  • Client/ Contractor: TransCo/ Alpha Omega Integrated Corporation
  • Date Awarded/ Completed: July 2005 – July 2006
  • Works done: Civil, Erection and Fabrication Works